Purpose

To deliver EU-funded project obligations (deliverables, milestones, reporting) on time, with clear internal ownership, and without disrupting core platform work.

Owner

Predrag Tasevski — Stakeholder & EU Projects Management

Trigger

This process starts at the beginning of each active EU project reporting period, or when a new deliverable milestone is due within the next 60 days.

Steps

  1. Deliverable mapping — At the start of each project period (or quarter), Ksenija maps all upcoming deliverables and milestones into OpenProject. Each deliverable becomes a task with: title, due date, assigned contributor(s), and project code. \\Tool: OpenProject
  2. Contributor assignment — For each deliverable requiring input from Predrag, Peter, or Alexander, Ksenija assigns the task in OpenProject and notifies via Matrix (#eu-projects channel). \\Tool: OpenProject, Matrix
  3. Weekly status check — Each Monday (before the L10 meeting), Ksenija updates the EU project deliverables on track (%) Scorecard metric in OpenProject. Any deliverable at risk goes on the Issues List. \\Tool: OpenProject
  4. Deliverable drafted — The assigned contributor produces the deliverable content. Format follows the project consortium's template. Stored in the project folder in Nextcloud under /EU Projects/[Project Name]/Deliverables/. \\Tool: Nextcloud, relevant EU project template
  5. Internal review — Alexander reviews the draft for completeness and compliance with the grant agreement requirements. Predrag reviews for strategic alignment if the deliverable is public-facing. \\Tool: Nextcloud
  6. Consortium review — Draft shared with consortium partners via the project's communication channel (email or project platform) for partner review and input. Incorporate feedback. \\Tool: Email / project consortium platform
  7. Submission — Final deliverable submitted via the EU project portal (e.g., PPMI, Funding & Tenders) by the due date. Ksenija confirms submission and saves the submission confirmation in Nextcloud. \\Tool: EU project portal, Nextcloud
  8. Milestone reported — Alexander marks the task as complete in OpenProject and updates the project tracker. Notifies Predrag for financial/reporting records if the milestone triggers a payment. \\Tool: OpenProject
  9. Financial claim (if applicable) — If the milestone triggers a payment claim, Predrag prepares the financial report in coordination with the project's financial controller and submits via the portal. \\Tool: Dolibarr (time tracking), EU project portal

Output

The process is complete when:

Tools

Active EU Projects

Project Role Coordinator Portal
OSCRAT Partner Predrag TBD
VIC Partner Predrag TBD
CyberSec4OT Partner Predrag TBD
SAFE SPORT Partner Predrag TBD

Update this table when projects are added or completed.